Progress Sheet

Ahmed Janahi Villa

Client — Ahmed Janahi

Project Completion
54%
Contract: QAR 1,188,850Earned: QAR 638,285

1

Villa

54%

Overall Completion

QAR 1,188,850.21

Contract Value

QAR 638,285.45

Earned Value

Completion: 54%

·

Contract value: QAR 1,188,850.21

·

Earned: QAR 638,285.45

ItemDescriptionQuantity% DoneActions
GENERAL
75%
A.1

Allow for project manager and project coordination, obtaining Landlord work permits, maintance permit, and necessary inspections.

N/A
1
75%
A.2

Provision for scaffoldings, adequate lighting, fire extinguishers, first aid kit and material protections such as plastic coverings or casing of the existing floor, wall or ceiling finishes at site.

N/A
1
75%
A.3

Allow for clearing of all debris/rubbish from site on a day to day basis keeping the site workable at all times

N/A
1
75%
A.4

Allow for final cleaning

N/A
1
75%
FLOOR FINISHES
90%
B.1.1

Supply & apply hand mixed sand cement screed for all floor Cement from local brand made in Qatar for up to 15cm

N/A
561m²
100%
B.1.2

Installation of floor tiles with work related materials like tile adhessive , tiles grout , spacer. tiles supplied by client( TILES BY CLIENT SUPPLY( Marble glue to be local brand)

N/A
561m²
100%
B.1.3

Installation of main stairs Marble or Ceramic tiles with adhessive & finished with special grout , tiles supplied by client( tiles glue and materials from a local brand)

N/A
1
0%
B.1.4

Supply & apply Bitumin paint & 4mm membrane sheet & upto 150Mm sand cement screed for ALL BATHROOM floors( Bitumin and Membrane to be from a local brand)

N/A
23m²
100%
WALL FINISHES
85%
B.1

Supply and install hand mix wall plaster ALL exterior walls( cement to be from a local brand) Including Boundary wall

N/A
885m²
100%
B.2

Supply & apply 1 coat primer , 2 coat stucco & final coats fenomastic matt paint for all internal wall to be determined by consultant ( PRICE INCLUDES STICHING AND CRACK REPAIRS for interior plaster WHERE NEEDED) including boundary wall

N/A
1,137m²
89%
B.3

TEXTURED JOTUN EXTERIOR PAINT 1 COAT PRIMER AND 2 COATS FINAL PAINT

N/A
759m²
57%
B.4

Installation ONLY of wall tiles ( Wet areas & kitchen )with work related materials like tile adhessive , tiles grout , spacer.( all transition strips supplied by client)TILES SUPPLIED BY CLIENT( MATERIALS FROM LOCAL MAKE AND BRAND)

N/A
168m²
100%
B.5

Supply & installation of hollow block with plaster finish for outside shaft

N/A
36
100%
B.6

Supply and install hollow blocks to make changes to interior walls including plaster and including breaking existing walls as per consultant drawings)

N/A
1
100%
B.8

GF WALL cladding GYPSUM WORK cladding with led lights including moulding( Materials to be from a local brand chosen by supplier)

N/A
60
0%
WALL MOULDING DESIGNS
GROUND FLOOR
0%
D.1

DINING

N/A
80
0%
D.2

SITTING 1

N/A
160
0%
D.3

SITTING 2

N/A
80
0%
D.4

FAMILY HALL

N/A
95
0%
FIRST FLOOR
0%
D.6

BEDROOM 1

N/A
182
0%
D.7

BEDROOM 2

N/A
168
0%
D.8

BEDROOM 3

N/A
182
0%
D.9

MASTER BEDROOM

N/A
308
0%
CEILING FINISHES
91%
C.1

Supply & installation of double step 12mm gypsum board ceiling with thread rod and C channel clip suspension system for GF & FF & annexes (standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier( INCLUDING CEILING CORNICH AS PER CLIENT REQUESTED DESIGN)

N/A
561m²
92%
C.2

Supply & installation of single step 12mm regular gypsum board ceiling with thread rod and C channel clip suspension system for PH (standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier

N/A
36m²
82%
C.3

Supply & apply joint tape finish , 1 coat primer , 2 coat stucco & 2 coat Jotun interior matt paint for all ceiling

N/A
561m²
86%
MEP
91%
G.1

Supply & installation of all piping , wirring , backbox , Main DB & others DB include all circuit breaker , armoured cables , Isolator , Installation of all fixtures , lights, bitumen for holding tank , Db testing & commissioning .( Budget ofSockets and switches and spot lights to be from china basic white QAR 10 per item) ( Chandlier and led strips excluded , All fixtures , lights AND SOCKETS TO BE BASIC WHITE SAMPLES TO BE SUBMITED) (All materials to be turkish or Oman)

N/A
1
91%
MEP
LOW VOLTAGE
100%
D.2

Low power : Supply & Install Piping , wirring & backbox work , fixtures installation only ( fixtures supplied by client )

N/A
1
100%
PLUMBING
92%
D.3

Supply & install all drainage pipes & fittings, connect pipe each manhole covers and bitumen finishing . Supply & install all water supply pipes , fittings , Water pump , water heater , Water tank as per materials specification page . Installation of all bathroom sanitery ware and vanities, tap , mixers ( water supply pipes Turkish or Oman) ( pump System European) (ALL VANITIES, BASINS , TOILETS AND BATHROOM ACCESSORIES SUPPLIED BY CLIENT)

N/A
1
90%
D.4

Supply & installation of Bitumin paint , 4mm membrane sheet , 4cm thermal insulation foam with GEO textile & upto 5cm concrete screed for Rooftop & roof deck AND ANNEX BUILDINGS with waterproof paint and texture cloth( completed and done ny TADMUR)

N/A
245m²
100%
Joinery
50%
E.1

Supply and Installation of main door of villa UPVC/WPC AND ALUMINIUM TO MATCH MAIN DOOR 3D AS BEST AS POSSIBLE COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT

N/A
1
0%
E.3

Supply and Installation of UPVC Windows for villa ( Turkish Black UPVC)DOUBLE GLAZED GLASS COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT

N/A
1
61%
E.5

Supply and Installation of Glass Balustrade FOR MAIN VILLA STAIRS with red oak or meranti solid Timber Handrail 50mm x 50mm- glass to be single 12mm tempered wall mounted with stainless steel fittings european brand and make

N/A
1
0%
Civil
0%
F.1

Construction of new room on top of outside kitchen with hollowblock and concrete maximum of 4000mm HIGHT x 4000mm WIDTH x 5000mm LENGHT( materials to be of a local make and brand

N/A
20
0%
Landscapping
0%
G.1

Installation ONLY of tiles for around of the EXTERIOR OF THE villa /TILES SUPPLIED BY CLIENT/ INCLUDED any backfill( Materials to be of local brand)

N/A
220
0%
G.2

Supply & install boundry gate AS PER DESIGN FOR CAR ENTERANCE and small GATE FOR PEDESTRIANS AS PER DESIGN (MATERIALS TO BE MILD STEEL WITH BLACK HIGH STRENGTH MATT MASS PAINTS FINISH)) ( 80MMX40MM FRAME ON TRACK WITH WHEELS 4MM INNER PLATED DESIGN TO MATCH RENDER) ( AUTOMATIC GATE MOTOR INCLUDED BRAND TO BE FROM EUROPE)

N/A
1
0%
VO-01 Demolition & Block Work
100%
1.1

Demolition of wall (400mm x 2900mm) — bathroom, including removal and disposal of debris.

N/A
1.16m²
100%
1.1

Demolition of wall (1500mm x 3500mm) — family hall, including removal and disposal of debris.

N/A
5.25m²
100%
1.1

Demolition of wall (400mm x 2900mm) — bathroom under stairs, including removal and disposal of debris.

N/A
1.16m²
100%
1.1

Demolition of wall (1500mm x 1260mm) — kids play room, including removal and disposal of debris.

N/A
1.89m²
100%
1.1

Building new wall (3950mm x 400mm) — kids play room.

N/A
1.58m²
100%
1.1

Demolition of wall (900mm x 2900mm) — master bathroom.

N/A
2.61m²
100%
1.1

Demolition of wall (900mm x 2900mm) — master bathroom [2].

N/A
2.61m²
100%
1.1

Demolition of wall (900mm x 2900mm) — dressing master.

N/A
2.61m²
100%
1.1

Demolition of wall (4900mm x 3820mm) — dressing master.

N/A
18.7m²
100%
1.1

Building new wall (4900mm x 3820mm) — dressing master.

N/A
18.7m²
100%
1.1

Building new wall (3160mm x 4000mm) — dressing master.

N/A
12.64m²
100%
1.1

Building new wall (3600mm x 3800mm) — ironing.

N/A
13.68m²
100%
1.1

Building new wall (3950mm x 3950mm) — dressing bedroom 1.

N/A
15.6m²
100%
1.1

Demolition of wall (400mm x 2900mm) — bathroom.

N/A
1.16m²
100%
1.1

Demolition of wall (3360mm x 3950mm) — bathroom.

N/A
13.2m²
100%
1.1

Building new wall (3360mm x 3950mm) — bathroom.

N/A
13.2m²
100%
1.1

Demolition of wall (400mm x 2900mm) — bathroom bedroom 2.

N/A
1.16m²
100%
VO-01 Electrical Changes
100%
6.1

Relocate wall light points (piping, wiring and chipping).

N/A
24
100%
6.2

Relocate switch points (piping, wiring and chipping).

N/A
21
100%
6.3

Relocate sockets (piping, wiring and chipping).

N/A
33
100%
6.4

Relocate AC thermostat points (piping, wiring and chipping).

N/A
4
100%
6.5

Relocate AC drainage points (piping, wiring and chipping).

N/A
2
100%
6.6

Relocate TV sockets (piping, wiring and chipping).

N/A
1
100%
6.7

Relocate data points (piping, wiring and chipping).

N/A
1
100%
6.8

Relocate intercom points (piping, wiring and chipping).

N/A
—
100%
6.1

New switches and sockets (piping, wiring and chipping).

N/A
15
100%
VO-01 Plumbing Changes
100%
6.1

Relocate floor drain.

N/A
1
100%
6.1

Relocate exhaust fan.

N/A
1
100%
VO-02 Boundary Blockwork
100%
1.1

Supply and install additional blockwork to the boundary walls to increase the height by two (2) blocks.

N/A
1
100%
VO-02 Waterproofing Flashing
0%
1.1

Supply and installation of aluminium flashing as an additional item to the originally quoted waterproofing works.

N/A
1
0%
VO-03 Additional Block Work
100%
1.1.2

Supply and installation of additional single-layer block work to all boundary walls (3 block courses per site instruction).

N/A
1
100%
VO-03 Bedroom Ceiling Switching
100%
1.1.3

Changes to bedroom ceiling light switching system — two-way loop switching for all bedrooms.

N/A
1
100%
VO-07.1 Doors
0%
1.1.1

Supply and install single swing door, MDF + veneer, W1000 x H2300mm.

N/A
12
0%
1.1.2

Supply and install double sliding door, MDF + veneer, W2000 x H2300mm.

N/A
1
0%
1.1.3

Supply and install single arch frame, red oak solid wood & veneer, W1000 x H2300mm.

N/A
4
0%
1.1.4

Supply and install double swing door, MDF + veneer, W1400 x H3800mm.

N/A
1
0%
VO-07.2 Omani Wall Stone
0%
1.1.5

Supply and install Omani stone cladding with mechanical fixation (50% of Majlis).

N/A
271m²
0%
VO-08.4 Parquet
0%
1.1.12

Supply and install premium European waterproof engineered parquet flooring, 20mm x 120mm planks with acoustic underlay.

N/A
229m²
0%
VO-07.3 Shower Glass
0%
1.1.8

Supply and install 12mm tempered clear glass shower partitions (all bathrooms).

N/A
1
0%
VO-07.5 Exterior Tiles Walkway
48%
1.1.12

Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (walkway & driveway).

N/A
175m²
48%
VO-07.6 Exterior Tiles PH Balcony
55%
1.1.12

Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (PH balcony).

N/A
85m²
55%
VO-07.7 Stairs Marble
0%
1.1.12

Supply and install Crema Marfil marble stairs (Grade A), 35cm treads + 16cm risers with concealed LED strip lighting.

N/A
1
0%
VO-08.1 Marble Vanity
0%
1.1.12

Supply and install Crema Marfil marble vanity top (Grade A), incl. fabrication and cut-outs.

N/A
5
0%
VO-08.2 Marble Thresholds
0%
1.1.12

Supply and install Crema Marfil marble thresholds (Grade A), 1000mm x 200mm (incl. 2 pcs for double door exits and main).

N/A
16
0%
VO-08.3 Car Shade
0%
1.1.12

Supply and install custom car shade 6000mm x 5000mm, galvanized steel frame, PVC ceiling.

N/A
1
0%
VO-08.4 Water Holding Tank
45%
1.1.12

Underground drinking water holding tank 2500mm x 2500mm x 2000mm — reinforced concrete, complete.

N/A
1
45%

Notes of the Day

No notes for today yet.

Submittals

0 total

No submittals uploaded yet.

Daily Progress Photos

03 Nov 2026· 14 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
25 Oct 2026· 22 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
24 Oct 2026· 33 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
21 Oct 2026· 8 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
13 Oct 2026· 30 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
12 Oct 2026· 36 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
11 Oct 2026· 37 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
10 Oct 2026· 51 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
07 Oct 2026· 41 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
27 Sep 2026· 25 photos
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress
Site progress

Ahmed Janahi Villa

Bill of Quantities · Progress Tracker · Rev 6 · 26/3/2026 · Prepared for Ahmed Janahi