1
Villa
54%
Overall Completion
QAR 1,188,850.21
Contract Value
QAR 638,285.45
Earned Value
Completion: 54%
·
Contract value: QAR 1,188,850.21
·
Earned: QAR 638,285.45
| Item | Description | Unit | Quantity | Rate | Total | % Done | Actions |
|---|---|---|---|---|---|---|---|
GENERAL QAR 39,589 75% | |||||||
A.1 | Allow for project manager and project coordination, obtaining Landlord work permits, maintance permit, and necessary inspections. N/A | item | 1 | 17,050 | QAR 17,050 | 75% | |
A.2 | Provision for scaffoldings, adequate lighting, fire extinguishers, first aid kit and material protections such as plastic coverings or casing of the existing floor, wall or ceiling finishes at site. N/A | item | 1 | 4,345 | QAR 4,345 | 75% | |
A.3 | Allow for clearing of all debris/rubbish from site on a day to day basis keeping the site workable at all times N/A | item | 1 | 9,394 | QAR 9,394 | 75% | |
A.4 | Allow for final cleaning N/A | item | 1 | 8,800 | QAR 8,800 | 75% | |
FLOOR FINISHES QAR 80,019 90% | |||||||
B.1.1 | Supply & apply hand mixed sand cement screed for all floor Cement from local brand made in Qatar for up to 15cm N/A | Sqm | 561m² | 66 | QAR 37,026 | 100% | |
B.1.2 | Installation of floor tiles with work related materials like tile adhessive , tiles grout , spacer. tiles supplied by client( TILES BY CLIENT SUPPLY( Marble glue to be local brand) N/A | Sqm | 561m² | 61 | QAR 33,941 | 100% | |
B.1.3 | Installation of main stairs Marble or Ceramic tiles with adhessive & finished with special grout , tiles supplied by client( tiles glue and materials from a local brand) N/A | Lot | 1 | 7,810 | QAR 7,810 | 0% | |
B.1.4 | Supply & apply Bitumin paint & 4mm membrane sheet & upto 150Mm sand cement screed for ALL BATHROOM floors( Bitumin and Membrane to be from a local brand) N/A | Sqm | 23m² | 54 | QAR 1,242 | 100% | |
WALL FINISHES QAR 118,337 85% | |||||||
B.1 | Supply and install hand mix wall plaster ALL exterior walls( cement to be from a local brand) Including Boundary wall N/A | Sqm | 885m² | 61 | QAR 53,543 | 100% | |
B.2 | Supply & apply 1 coat primer , 2 coat stucco & final coats fenomastic matt paint for all internal wall to be determined by consultant ( PRICE INCLUDES STICHING AND CRACK REPAIRS for interior plaster WHERE NEEDED) including boundary wall N/A | Sqm | 1,137m² | 17 | QAR 18,761 | 89% | |
B.3 | TEXTURED JOTUN EXTERIOR PAINT 1 COAT PRIMER AND 2 COATS FINAL PAINT N/A | Sqm | 759m² | 24 | QAR 18,216 | 57% | |
B.4 | Installation ONLY of wall tiles ( Wet areas & kitchen )with work related materials like tile adhessive , tiles grout , spacer.( all transition strips supplied by client)TILES SUPPLIED BY CLIENT( MATERIALS FROM LOCAL MAKE AND BRAND) N/A | Sqm | 168m² | 66 | QAR 11,088 | 100% | |
B.5 | Supply & installation of hollow block with plaster finish for outside shaft N/A | Lm | 36 | 116 | QAR 4,158 | 100% | |
B.6 | Supply and install hollow blocks to make changes to interior walls including plaster and including breaking existing walls as per consultant drawings) N/A | Lot | 1 | 5,012 | QAR 5,012 | 100% | |
B.8 | GF WALL cladding GYPSUM WORK cladding with led lights including moulding( Materials to be from a local brand chosen by supplier) N/A | sqm | 60 | 126 | QAR 7,560 | 0% | |
| WALL MOULDING DESIGNS | |||||||
GROUND FLOOR QAR 3,984 0% | |||||||
D.1 | DINING N/A | LM | 80 | 10 | QAR 768 | 0% | |
D.2 | SITTING 1 N/A | LM | 160 | 10 | QAR 1,536 | 0% | |
D.3 | SITTING 2 N/A | LM | 80 | 10 | QAR 768 | 0% | |
D.4 | FAMILY HALL N/A | LM | 95 | 10 | QAR 912 | 0% | |
FIRST FLOOR QAR 8,064 0% | |||||||
D.6 | BEDROOM 1 N/A | LM | 182 | 10 | QAR 1,747 | 0% | |
D.7 | BEDROOM 2 N/A | LM | 168 | 10 | QAR 1,613 | 0% | |
D.8 | BEDROOM 3 N/A | LM | 182 | 10 | QAR 1,747 | 0% | |
D.9 | MASTER BEDROOM N/A | LM | 308 | 10 | QAR 2,957 | 0% | |
CEILING FINISHES QAR 72,282 91% | |||||||
C.1 | Supply & installation of double step 12mm gypsum board ceiling with thread rod and C channel clip suspension system for GF & FF & annexes (standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier( INCLUDING CEILING CORNICH AS PER CLIENT REQUESTED DESIGN) N/A | Sqm | 561m² | 108 | QAR 60,588 | 92% | |
C.2 | Supply & installation of single step 12mm regular gypsum board ceiling with thread rod and C channel clip suspension system for PH (standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier N/A | Sqm | 36m² | 102 | QAR 3,672 | 82% | |
C.3 | Supply & apply joint tape finish , 1 coat primer , 2 coat stucco & 2 coat Jotun interior matt paint for all ceiling N/A | Sqm | 561m² | 14 | QAR 8,022 | 86% | |
MEP QAR 144,000 91% | |||||||
G.1 | Supply & installation of all piping , wirring , backbox , Main DB & others DB include all circuit breaker , armoured cables , Isolator , Installation of all fixtures , lights, bitumen for holding tank , Db testing & commissioning .( Budget ofSockets and switches and spot lights to be from china basic white QAR 10 per item) ( Chandlier and led strips excluded , All fixtures , lights AND SOCKETS TO BE BASIC WHITE SAMPLES TO BE SUBMITED) (All materials to be turkish or Oman) N/A | Item | 1 | 144,000 | QAR 144,000 | 91% | |
| MEP | |||||||
LOW VOLTAGE QAR 8,400 100% | |||||||
D.2 | Low power : Supply & Install Piping , wirring & backbox work , fixtures installation only ( fixtures supplied by client ) N/A | Lot | 1 | 8,400 | QAR 8,400 | 100% | |
PLUMBING QAR 120,990 92% | |||||||
D.3 | Supply & install all drainage pipes & fittings, connect pipe each manhole covers and bitumen finishing . Supply & install all water supply pipes , fittings , Water pump , water heater , Water tank as per materials specification page . Installation of all bathroom sanitery ware and vanities, tap , mixers ( water supply pipes Turkish or Oman) ( pump System European) (ALL VANITIES, BASINS , TOILETS AND BATHROOM ACCESSORIES SUPPLIED BY CLIENT) N/A | Lot | 1 | 96,000 | QAR 96,000 | 90% | |
D.4 | Supply & installation of Bitumin paint , 4mm membrane sheet , 4cm thermal insulation foam with GEO textile & upto 5cm concrete screed for Rooftop & roof deck AND ANNEX BUILDINGS with waterproof paint and texture cloth( completed and done ny TADMUR) N/A | Sqm | 245m² | 102 | QAR 24,990 | 100% | |
Joinery QAR 155,303 50% | |||||||
E.1 | Supply and Installation of main door of villa UPVC/WPC AND ALUMINIUM TO MATCH MAIN DOOR 3D AS BEST AS POSSIBLE COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT N/A | Item | 1 | 8,220 | QAR 8,220 | 0% | |
E.3 | Supply and Installation of UPVC Windows for villa ( Turkish Black UPVC)DOUBLE GLAZED GLASS COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT N/A | Item | 1 | 127,200 | QAR 127,200 | 61% | |
E.5 | Supply and Installation of Glass Balustrade FOR MAIN VILLA STAIRS with red oak or meranti solid Timber Handrail 50mm x 50mm- glass to be single 12mm tempered wall mounted with stainless steel fittings european brand and make N/A | Item | 1 | 19,883 | QAR 19,883 | 0% | |
Civil QAR 27,600 0% | |||||||
F.1 | Construction of new room on top of outside kitchen with hollowblock and concrete maximum of 4000mm HIGHT x 4000mm WIDTH x 5000mm LENGHT( materials to be of a local make and brand N/A | sqm | 20 | 1,380 | QAR 27,600 | 0% | |
Landscapping QAR 36,410 0% | |||||||
G.1 | Installation ONLY of tiles for around of the EXTERIOR OF THE villa /TILES SUPPLIED BY CLIENT/ INCLUDED any backfill( Materials to be of local brand) N/A | sqm | 220 | 63 | QAR 13,860 | 0% | |
G.2 | Supply & install boundry gate AS PER DESIGN FOR CAR ENTERANCE and small GATE FOR PEDESTRIANS AS PER DESIGN (MATERIALS TO BE MILD STEEL WITH BLACK HIGH STRENGTH MATT MASS PAINTS FINISH)) ( 80MMX40MM FRAME ON TRACK WITH WHEELS 4MM INNER PLATED DESIGN TO MATCH RENDER) ( AUTOMATIC GATE MOTOR INCLUDED BRAND TO BE FROM EUROPE) N/A | unit | 1 | 22,550 | QAR 22,550 | 0% | |
VO-01 Demolition & Block Work QAR 8,735 100% | |||||||
1.1 | Demolition of wall (400mm x 2900mm) — bathroom, including removal and disposal of debris. N/A | SQM | 1.16m² | 43 | QAR 50 | 100% | |
1.1 | Demolition of wall (1500mm x 3500mm) — family hall, including removal and disposal of debris. N/A | SQM | 5.25m² | 43 | QAR 225 | 100% | |
1.1 | Demolition of wall (400mm x 2900mm) — bathroom under stairs, including removal and disposal of debris. N/A | SQM | 1.16m² | 43 | QAR 50 | 100% | |
1.1 | Demolition of wall (1500mm x 1260mm) — kids play room, including removal and disposal of debris. N/A | SQM | 1.89m² | 43 | QAR 81 | 100% | |
1.1 | Building new wall (3950mm x 400mm) — kids play room. N/A | SQM | 1.58m² | — | — | 100% | |
1.1 | Demolition of wall (900mm x 2900mm) — master bathroom. N/A | SQM | 2.61m² | 43 | QAR 112 | 100% | |
1.1 | Demolition of wall (900mm x 2900mm) — master bathroom [2]. N/A | SQM | 2.61m² | 43 | QAR 112 | 100% | |
1.1 | Demolition of wall (900mm x 2900mm) — dressing master. N/A | SQM | 2.61m² | 43 | QAR 112 | 100% | |
1.1 | Demolition of wall (4900mm x 3820mm) — dressing master. N/A | SQM | 18.7m² | 43 | QAR 802 | 100% | |
1.1 | Building new wall (4900mm x 3820mm) — dressing master. N/A | SQM | 18.7m² | 88 | QAR 1,653 | 100% | |
1.1 | Building new wall (3160mm x 4000mm) — dressing master. N/A | SQM | 12.64m² | 88 | QAR 1,117 | 100% | |
1.1 | Building new wall (3600mm x 3800mm) — ironing. N/A | SQM | 13.68m² | 88 | QAR 1,209 | 100% | |
1.1 | Building new wall (3950mm x 3950mm) — dressing bedroom 1. N/A | SQM | 15.6m² | 88 | QAR 1,379 | 100% | |
1.1 | Demolition of wall (400mm x 2900mm) — bathroom. N/A | SQM | 1.16m² | 43 | QAR 50 | 100% | |
1.1 | Demolition of wall (3360mm x 3950mm) — bathroom. N/A | SQM | 13.2m² | 43 | QAR 566 | 100% | |
1.1 | Building new wall (3360mm x 3950mm) — bathroom. N/A | SQM | 13.2m² | 88 | QAR 1,167 | 100% | |
1.1 | Demolition of wall (400mm x 2900mm) — bathroom bedroom 2. N/A | SQM | 1.16m² | 43 | QAR 50 | 100% | |
VO-01 Electrical Changes QAR 5,909 100% | |||||||
6.1 | Relocate wall light points (piping, wiring and chipping). N/A | POINTS | 24 | 59 | QAR 1,404 | 100% | |
6.2 | Relocate switch points (piping, wiring and chipping). N/A | POINTS | 21 | 59 | QAR 1,229 | 100% | |
6.3 | Relocate sockets (piping, wiring and chipping). N/A | POINTS | 33 | 59 | QAR 1,931 | 100% | |
6.4 | Relocate AC thermostat points (piping, wiring and chipping). N/A | POINTS | 4 | 59 | QAR 234 | 100% | |
6.5 | Relocate AC drainage points (piping, wiring and chipping). N/A | POINTS | 2 | 59 | QAR 117 | 100% | |
6.6 | Relocate TV sockets (piping, wiring and chipping). N/A | POINTS | 1 | 59 | QAR 59 | 100% | |
6.7 | Relocate data points (piping, wiring and chipping). N/A | POINTS | 1 | 59 | QAR 59 | 100% | |
6.8 | Relocate intercom points (piping, wiring and chipping). N/A | POINTS | — | 59 | — | 100% | |
6.1 | New switches and sockets (piping, wiring and chipping). N/A | POINTS | 15 | 59 | QAR 878 | 100% | |
VO-01 Plumbing Changes QAR 143 100% | |||||||
6.1 | Relocate floor drain. N/A | POINTS | 1 | 85 | QAR 85 | 100% | |
6.1 | Relocate exhaust fan. N/A | POINTS | 1 | 59 | QAR 59 | 100% | |
VO-02 Boundary Blockwork QAR 4,048 100% | |||||||
1.1 | Supply and install additional blockwork to the boundary walls to increase the height by two (2) blocks. N/A | LOT | 1 | 4,048 | QAR 4,048 | 100% | |
VO-02 Waterproofing Flashing QAR 3,072 0% | |||||||
1.1 | Supply and installation of aluminium flashing as an additional item to the originally quoted waterproofing works. N/A | LOT | 1 | 3,072 | QAR 3,072 | 0% | |
VO-03 Additional Block Work QAR 1,746 100% | |||||||
1.1.2 | Supply and installation of additional single-layer block work to all boundary walls (3 block courses per site instruction). N/A | LOT | 1 | 1,746 | QAR 1,746 | 100% | |
VO-03 Bedroom Ceiling Switching QAR 2,710 100% | |||||||
1.1.3 | Changes to bedroom ceiling light switching system — two-way loop switching for all bedrooms. N/A | LOT | 1 | 2,710 | QAR 2,710 | 100% | |
VO-07.1 Doors QAR 75,895 0% | |||||||
1.1.1 | Supply and install single swing door, MDF + veneer, W1000 x H2300mm. N/A | item | 12 | 4,128 | QAR 49,536 | 0% | |
1.1.2 | Supply and install double sliding door, MDF + veneer, W2000 x H2300mm. N/A | item | 1 | 8,664 | QAR 8,664 | 0% | |
1.1.3 | Supply and install single arch frame, red oak solid wood & veneer, W1000 x H2300mm. N/A | item | 4 | 1,648 | QAR 6,590 | 0% | |
1.1.4 | Supply and install double swing door, MDF + veneer, W1400 x H3800mm. N/A | item | 1 | 11,105 | QAR 11,105 | 0% | |
VO-07.2 Omani Wall Stone QAR 113,820 0% | |||||||
1.1.5 | Supply and install Omani stone cladding with mechanical fixation (50% of Majlis). N/A | SQM | 271m² | 420 | QAR 113,820 | 0% | |
VO-08.4 Parquet QAR 32,976 0% | |||||||
1.1.12 | Supply and install premium European waterproof engineered parquet flooring, 20mm x 120mm planks with acoustic underlay. N/A | SQM | 229m² | 144 | QAR 32,976 | 0% | |
VO-07.3 Shower Glass QAR 14,949 0% | |||||||
1.1.8 | Supply and install 12mm tempered clear glass shower partitions (all bathrooms). N/A | LOT | 1 | 14,949 | QAR 14,949 | 0% | |
VO-07.5 Exterior Tiles Walkway QAR 15,680 48% | |||||||
1.1.12 | Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (walkway & driveway). N/A | SQM | 175m² | 90 | QAR 15,680 | 48% | |
VO-07.6 Exterior Tiles PH Balcony QAR 7,616 55% | |||||||
1.1.12 | Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (PH balcony). N/A | SQM | 85m² | 90 | QAR 7,616 | 55% | |
VO-07.7 Stairs Marble QAR 31,200 0% | |||||||
1.1.12 | Supply and install Crema Marfil marble stairs (Grade A), 35cm treads + 16cm risers with concealed LED strip lighting. N/A | UMIT | 1 | 31,200 | QAR 31,200 | 0% | |
VO-08.1 Marble Vanity QAR 16,200 0% | |||||||
1.1.12 | Supply and install Crema Marfil marble vanity top (Grade A), incl. fabrication and cut-outs. N/A | UMIT | 5 | 3,240 | QAR 16,200 | 0% | |
VO-08.2 Marble Thresholds QAR 4,992 0% | |||||||
1.1.12 | Supply and install Crema Marfil marble thresholds (Grade A), 1000mm x 200mm (incl. 2 pcs for double door exits and main). N/A | UMIT | 16 | 312 | QAR 4,992 | 0% | |
VO-08.3 Car Shade QAR 19,902 0% | |||||||
1.1.12 | Supply and install custom car shade 6000mm x 5000mm, galvanized steel frame, PVC ceiling. N/A | UMIT | 1 | 19,902 | QAR 19,902 | 0% | |
VO-08.4 Water Holding Tank QAR 14,280 45% | |||||||
1.1.12 | Underground drinking water holding tank 2500mm x 2500mm x 2000mm — reinforced concrete, complete. N/A | LS | 1 | 14,280 | QAR 14,280 | 45% | |
Notes of the Day
No notes for today yet.
Submittals
0 totalNo submittals uploaded yet.
Daily Progress Photos