1
Villa
62%
Overall Completion
QAR 1,477,781.48
Contract Value
QAR 919,700.27
Earned Value
Completion: 62%
·
Contract value: QAR 1,477,781.48
·
Earned: QAR 919,700.27
| Item | Description | Unit | Quantity | Rate | Total | % Done | Actions |
|---|---|---|---|---|---|---|---|
GENERAL QAR 39,589 91% | |||||||
A.1 | Allow for project manager and project coordination, obtaining Landlord work permits, maintance permit, and necessary inspections. N/A | item | 1 | 17,050 | QAR 17,050 | 91% | |
A.2 | Allow for clearing of all debris/rubbish from site on a day to day basis keeping the site workable at all times N/A | item | 1 | 4,345 | QAR 4,345 | 100% | |
A.3 | Allow for site establishment, including mobilization, maintenance during construction period of temporary equipment on project completion N/A | item | 1 | 9,394 | QAR 9,394 | 100% | |
A.4 | Allow for final cleaning N/A | item | 1 | 8,800 | QAR 8,800 | 75% | |
FLOOR FINISHES QAR 104,800 91% | |||||||
B.1 | Supply & apply hand mixed sand cement screed for all floor Cement from local brand made in Qatar for up to 15cm N/A | Sqm | 703m² | 60 | QAR 42,180 | 100% | |
B.2 | Installation of floor tiles with work related materials like tile adhessive , tiles grout , spacer. tiles supplied by client( TILES BY CLIENT SUPPLY( Marble glue to be local brand) N/A | Sqm | 703m² | 61 | QAR 42,532 | 94% | |
B.3 | Supply and Installation of Stairs Of solid meranti wood as per client design with led below and plaster and paint riser / or Ceramic steps with wood design with adhessive & finished with special grout incl led below and plaster and paint riser ( Marble glue to be local brand) N/A | Lot | 1 | 14,850 | QAR 14,850 | 52% | |
B.4 | Supply & apply Bitumin paint & 4mm membrane sheet & upto 150Mm sand cement screed for ALL BATHROOM floors( Bitumin and Membrane to be from a local brand) N/A | Sqm | 97m² | 54 | QAR 5,238 | 100% | |
WALL FINISHES AND CLADDING DESIGNS QAR 64,445 81% | |||||||
C.2 | Supply & apply 1 coat primer , 2 coat stucco & final coat to be determined by consultant, fenomastic matt paint for all internal wall ( PRICE INCLUDES STICHING AND CRACK REPAIRS OF WALL PLASTER WHERE NEEDED) N/A | Sqm | 1,535m² | 17 | QAR 26,172 | 75% | |
C.3 | Supply & apply 1 coat primer , 2 coat jotashield paint for external BOUNDRY wall N/A | Sqm | 477m² | 24 | QAR 11,543 | 52% | |
C.4 | Installation ONLY of wall tiles ( Wet areas & kitchen )with work related materials like tile adhessive , tiles grout , spacer.( all transition strips supplied by client)TILES SUPPLIED BY CLIENT( MATERIALS FROM LOCAL MAKE AND BRAND) N/A | Sqm | 405m² | 66 | QAR 26,730 | 100% | |
EXTERIOR ELEVATION QAR 42,725 57% | |||||||
C.1.4 | TEXTURED JOTUN EXTERIOR PAINT 1 COAT PRIMER AND 2 COATS FINAL PAINT N/A | Sqm | 1,150m² | 24 | QAR 27,600 | 58% | |
C.1.5 | ALUMINIUM DESIGN PANELS OVER WINDOWS / BLOCK WORK AND PLASTER OVER SHAFTS N/A | Sqm | 110m² | 138 | QAR 15,125 | 54% | |
| WALL MOULDING DESIGNS | |||||||
GROUND FLOOR QAR 3,898 0% | |||||||
D.1 | DINING N/A | LM | 56 | 10 | QAR 538 | 0% | |
D.2 | LIVING N/A | LM | 84 | 10 | QAR 806 | 0% | |
D.3 | LADIES MAJLIS4 N/A | LM | 196 | 10 | QAR 1,882 | 0% | |
D.4 | LIVING AREA N/A | LM | 70 | 10 | QAR 672 | 0% | |
FIRST FLOOR QAR 4,560 0% | |||||||
D.6 | BEDROOM 1 N/A | LM | 185 | 10 | QAR 1,776 | 0% | |
D.7 | BEDROOM 2 N/A | LM | 145 | 10 | QAR 1,392 | 0% | |
D.8 | BEDROOM 3 N/A | LM | 145 | 10 | QAR 1,392 | 0% | |
CIVIL QAR 115,050 66% | |||||||
E.5 | Supply & installation of hollow block with plaster finish for shaft N/A | Item | 1 | 4,950 | QAR 4,950 | 100% | |
E.6 | Supply & install boundry gate AS PER DESIGN FOR CAR ENTERANCE and small GATE FOR PEDESTRIANS AS PER DESIGN (MATERIALS TO BE MILD STEEL WITH BLACK HIGH STRENGTH MATT MASS PAINTS FINISH)) ( 80MMX40MM FRAME ON TRACK WITH WHEELS 4MM INNER PLATED DESIGN TO MATCH RENDER) ( AUTOMATIC GATE MOTOR INCLUDED BRAND TO BE FROM EUROPE) N/A | unit | 1 | 24,750 | QAR 24,750 | 0% | |
E.7 | Squaring off concrete on villa face TO MATCH THE DESIGN WITH 2 X SLABS ON TOP AND BOTTOM OF ALUMINIUM LOOVERS WITH HOLLOW BLOCK AND PLASTER N/A | unit | — | — | — | 100% | |
E.8 | Supply and install hand mix wall plaster for exterior walls( cement to be from a local brand)Including boundary wall plaster( quote excludes front of villa) N/A | sqm | 660 | 61 | QAR 39,930 | 100% | |
E.9 | Supply and install hollow blocks to make changes to interor walls including plaster and including breaking existing walls as per consultant drawings) N/A | sqm | 210 | 126 | QAR 26,460 | 100% | |
E.10 | Supply and install hollow blocks to make changes to interior wall in master bedroom bathroom to create niches as per design by client N/A | sqm | 10 | 126 | QAR 1,260 | 100% | |
E.11 | Supply and Construct concrete/steel slabs/roof for kitchen and penthouse extension including new columns as per required on site N/A | sqm | 10 | 1,380 | QAR 13,800 | 0% | |
E.12 | Supply and Construct BLOCK & PLASTER wall for kitchen to be demolished after completion certificate( single layer inside and single outside materials to be of local brand ,incl Paint and joint tape) N/A | lot | 1 | 3,900 | QAR 3,900 | 100% | |
CEILING FINISHES QAR 84,690 95% | |||||||
F.1 | Supply & installation of double step 12mm gypsum board ceiling with thread rod and C channel clip suspension system for GF & FF & annexes 600MMX600MM GRIP LAYOUT(standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier( INCLUDING CEILING CORNICH AS PER CLIENT REQUESTED DESIGN) N/A | Sqm | 535m² | 108 | QAR 57,780 | 95% | |
F.2 | Supply & installation of single step 12mm regular gypsum board ceiling with thread rod and C channel clip suspension system for PH (standard for open areas/ fire rated for kitchen and water resistant for wet area) All materials to be of a local brand chosen by supplier N/A | Sqm | 165m² | 102 | QAR 16,830 | 95% | |
F.3 | Supply & apply joint tape finish , 1 coat primer , 2 coat stucco & 2 coat Jotun interior matt paint for all ceiling N/A | Sqm | 700m² | 14 | QAR 10,080 | 95% | |
MEP QAR 268,050 94% | |||||||
G.1 | Supply & installation of all piping , wirring , backbox , Main DB & others DB include all circuit breaker , armoured cables , Isolator , Installation of all fixtures , lights, bitumen for holding tank , Db testing & commissioning .( Budget ofSockets and switches and spot lights to be from china basic white QAR 10 per item) ( Chandlier and led strips excluded , All fixtures , lights AND SOCKETS TO BE BASIC WHITE SAMPLES TO BE SUBMITED) (All materials to be turkish or Oman) N/A | Item | 1 | 144,000 | QAR 144,000 | 94% | |
G.3 | Supply & install all drainage pipes & fittings, connect pipe each manhole /supply covers and bitumen finishing . Supply & install all water supply pipes , fittings , Water pump , water heater , Water tank as per materials specification page . Installation of all bathroom sanitery ware and vanities, tap , mixers ( water supply pipes Turkish or Oman) ( pump System European) (ALL VANITIES, BASINS , TOILETS AND BATHROOM ACCESSORIES SUPPLIED BY CLIENT) N/A | Item | 1 | 96,000 | QAR 96,000 | 91% | |
G.4 | HVAC BY CLIENT NOT IN SCOPE( Plinth for outdoor units included in BR scope) N/A | Item | — | — | — | 100% | |
G.5 | Supply & installation of Bitumin paint , 4mm membrane sheet , 4cm thermal insulation foam with GEO textile & upto 5cm concrete screed for Rooftop & roof deck and annex buildings with waterproof paint and texture cloth( completed and done by TADMUR)( materials to be from Qatar or Saudi origin) N/A | Sqm | 275m² | 102 | QAR 28,050 | 100% | |
| MEP | |||||||
LOW VOLTAGE QAR 8,400 100% | |||||||
G.2 | Low power : Supply & Install Piping , wirring & backbox work , fixtures installation only ( fixtures supplied by client ) N/A | Item | 1 | 8,400 | QAR 8,400 | 100% | |
Doors & Windows QAR 159,315 89% | |||||||
H.1 | Supply and Installation of main door of villa UPVC/WPC AND ALUMINIUM TO MATCH MAIN DOOR 3D AS BEST AS POSSIBLE COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT N/A | Item | 1 | 8,220 | QAR 8,220 | 88% | |
H.2 | Supply and Installation of main door of Majlis UPVC/WPC AND ALUMINIUM TO MATCH MAIN DOOR 3D AS BEST AS POSSIBLE COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT N/A | Item | 1 | 8,220 | QAR 8,220 | 0% | |
H.3.1 | Supply and Installation of upvc or aluminium doors for non interior door locations ( IRONMONGERIES TO BE BASIC STAINLESS STEEL BRUSHED or black Chinese Make and model) N/A | Item | 9 | 1,475 | QAR 13,275 | 90% | |
H.4 | Supply and Installation of UPVC Windows for villa ( Turkish Black UPVC)DOUBLE GLAZED GLASS COLOUR TO BE SELECTED BY CONSULTANT AND CLIENT N/A | Item | 1 | 129,600 | QAR 129,600 | 95% | |
Elevator QAR 81,600 90% | |||||||
I.1 | Stainless steel elevator cabin with etched design finish, mirrors, and a 630 kg capacity. Model 6, MRL Elevator, 2024, suitable for indoor use. Warranty included. double sided entry( Brand Fuji) N/A | Item | 1 | 81,600 | QAR 81,600 | 90% | |
Joinery QAR 19,896 0% | |||||||
J.2 | GF TV WALL UNIT AS PER 3D DESIGN LIVING ROOM GYPSUM WORK ONLY TO MAKE TV UNIT NO WOOD OR MARBLE INCLUDED N/A | Item | 1 | 1,896 | QAR 1,896 | 0% | |
J.3 | GF WALL cladding GYPSUM WORK cladding with led lights including moulding( Materials to be from a local brand chosen by supplier) N/A | sqm | 60 | 132 | QAR 7,920 | 0% | |
J.4 | HAND RAIL FOR STAIRS MADE OUT OF Meranti solid WOOD STANDARD WALL MOUNTED 15CM X 7CM RAIL NOT AS PER 3D DESIGN ( inlcuding led strip below) N/A | Item | 1 | 10,080 | QAR 10,080 | 0% | |
Landscapping QAR 12,600 0% | |||||||
K.1 | Installation ONLY of tiles for around of the EXTERIOR OF THE villa /TILES SUPPLIED BY CLIENT/including any backfill( Materials to be of local brand) N/A | SQM | 200m² | 63 | QAR 12,600 | 0% | |
VO-01 Demolition & Block Work QAR 26,413 100% | |||||||
1.1 | Supply and install 10 cm blockwork above toilets in all bathrooms to create niches with concealed lighting, including all blockwork for additional walls in the bathrooms. N/A | LOT | 1 | 4,219 | QAR 4,219 | 100% | |
1.1 | Supply and install additional blockwork to the boundary walls to increase the height by two (2) blocks. N/A | LOT | 1 | 4,618 | QAR 4,618 | 100% | |
1.1 | Supply and install aluminium skirting profile flush with the wall, as per the client's request. (Budget for aluminium profile 20 QAR per meter) N/A | LM | 268 | 33 | QAR 8,710 | 100% | |
1.1 | Demolition of wall to make new window 1650mm x 1350mm (and removal of rubbish). N/A | SQM | 2.22m² | 43 | QAR 95 | 100% | |
1.1 | Demolition of wall partition 4200mm x 4200mm (and removal of rubbish). N/A | SQM | 17.64m² | 43 | QAR 757 | 100% | |
1.1 | Build new wall 4200mm x 4200mm. N/A | SQM | 17.64m² | 88 | QAR 1,559 | 100% | |
1.1.1 | Building new wall 8000mm x 3350mm (original — removed). N/A | SQM | 26.8m² | 88 | — | 100% | |
1.1.1 Rev | Building new wall 8000mm x 3350mm (revised). N/A | SQM | 2.68m² | 88 | QAR 237 | 100% | |
1.1.2 | Demolition of existing wall 8000mm x 335mm (and removal of rubbish). N/A | SQM | 26.8m² | 43 | QAR 1,150 | 100% | |
2.1 | Demolition of wall to make new door 2850mm x 2500mm (and removal of rubbish). N/A | SQM | 7.12m² | 43 | QAR 305 | 100% | |
2.1 | Demolition of wall to make new window 600mm x 3100mm (and removal of rubbish). N/A | SQM | 1.86m² | 43 | QAR 80 | 100% | |
2.1 | Modify, demolition reopen new door in bathroom 900mm x 2400mm (and removal of rubbish). N/A | SQM | 2.16m² | 103 | QAR 222 | 100% | |
2.1 | Modify, demolition reopen new door in dressing room 900mm x 2400mm (and removal of rubbish). N/A | SQM | 2.16m² | 103 | QAR 222 | 100% | |
3.1 | Demolition of bathroom 4250mm x 4000mm (and removal of rubbish). N/A | SQM | 16.8m² | 43 | QAR 721 | 100% | |
3.1 | Demolition of dressing room wall, new door 2400mm x 900mm (and removal of rubbish). N/A | SQM | 2.16m² | 103 | QAR 222 | 100% | |
3.1 | Demolition of bathroom room wall, new door 2400mm x 900mm (and removal of rubbish). N/A | SQM | 2.16m² | 103 | QAR 222 | 100% | |
3.1 | Demolition, modify new window closing old and making new opening in room 3160mm x 900mm (and removal of rubbish). N/A | SQM | 2.84m² | 103 | QAR 292 | 100% | |
3.1 | Demolition, modify new window closing old and making new opening in bathroom 3160mm x 600mm (and removal of rubbish). N/A | SQM | 2.84m² | 103 | QAR 292 | 100% | |
4.1 | Demolition of all bedroom walls 4250mm x 4000mm (and removal of rubbish). N/A | SQM | 17m² | 43 | QAR 729 | 100% | |
4.1 | Demolition, modify new window closing old and making new opening in room 3200mm x 1200mm (and removal of rubbish). N/A | SQM | 1.92m² | 103 | QAR 197 | 100% | |
4.1 | Demolition, modify new window closing old and making new opening in bathroom 3200mm x 600mm (and removal of rubbish). N/A | SQM | 1.92m² | 103 | QAR 197 | 100% | |
5.1 | Close existing window in pantry 600mm x 2700mm. N/A | SQM | 1.62m² | 88 | QAR 143 | 100% | |
5.1 | Close existing window in gym 1300mm x 2700mm. N/A | SQM | 3.51m² | 88 | QAR 310 | 100% | |
5.1 | Modify, demolition wall for new window in gym 1300mm x 2700mm (and removal of rubbish). N/A | SQM | 3.51m² | 103 | QAR 360 | 100% | |
5.1 | Modify, demolition wall for new window in gym 600mm x 2700mm (and removal of rubbish). N/A | SQM | 1.62m² | 103 | QAR 166 | 100% | |
5.1 | Modify, demolition wall for new window in gym 600mm x 2700mm (and removal of rubbish). [2] N/A | SQM | 1.62m² | 103 | QAR 166 | 100% | |
5.1 | Breaking / closing wall to relocate door 2400mm x 900mm (and removal of rubbish). N/A | SQM | 2.16m² | 103 | QAR 222 | 100% | |
VO-01 Electrical Changes QAR 10,121 100% | |||||||
6.1 | Relocate wall light points (piping, wiring and chipping). N/A | POINTS | 52 | 59 | QAR 3,042 | 100% | |
6.1 | Relocate switch points (piping, wiring and chipping). N/A | POINTS | 19 | 59 | QAR 1,112 | 100% | |
6.1 | Relocate sockets (piping, wiring and chipping). N/A | POINTS | 43 | 59 | QAR 2,516 | 100% | |
6.1 | Relocate AC thermostat points (piping, wiring and chipping). N/A | POINTS | 6 | 59 | QAR 351 | 100% | |
6.1 | Relocate AC drainage points (piping, wiring and chipping). N/A | POINTS | 5 | 59 | QAR 293 | 100% | |
6.1 | Relocate TV sockets (piping, wiring and chipping). N/A | POINTS | 6 | 59 | QAR 351 | 100% | |
6.1 | Relocate data points (piping, wiring and chipping). N/A | POINTS | 1 | 59 | QAR 59 | 100% | |
6.1 | Relocate intercom points (piping, wiring and chipping). N/A | POINTS | 1 | 59 | QAR 59 | 100% | |
6.1 | New switches and sockets (piping, wiring and chipping). N/A | POINTS | 40 | 59 | QAR 2,340 | 100% | |
VO-01 Plumbing Changes QAR 683 100% | |||||||
6.1 | Relocate floor drain. N/A | POINTS | 6 | 85 | QAR 507 | 100% | |
6.1 | Relocate exhaust fan. N/A | POINTS | 3 | 59 | QAR 176 | 100% | |
VO-02 Waterproofing Flashing QAR 3,120 0% | |||||||
1.1 | Supply and installation of aluminium flashing as an additional item to the originally quoted waterproofing works. N/A | LOT | 1 | 3,120 | QAR 3,120 | 0% | |
VO-03 Additional Block Work QAR 1,750 100% | |||||||
1.1.2 | Supply and installation of additional single-layer block work to all boundary walls (3 block courses per site instruction). N/A | LOT | 1 | 1,750 | QAR 1,750 | 100% | |
VO-03 Bedroom Ceiling Switching QAR 3,310 100% | |||||||
1.1.3 | Changes to bedroom ceiling light switching system — two-way loop switching for all bedrooms. N/A | LOT | 1 | 3,310 | QAR 3,310 | 100% | |
VO-04 Kitchen Revisions QAR 828 100% | |||||||
1.1.2 | Revisions to exterior kitchen wall lighting, electrical sockets, and power outlets. N/A | LOT | 1 | 414 | QAR 414 | 100% | |
1.1.3 | Revisions to interior kitchen wall lighting, electrical sockets, and power outlets. N/A | LOT | 1 | 414 | QAR 414 | 100% | |
VO-04 Gypsum & Niches QAR 3,250 100% | |||||||
1.1.4 | Supply and install gypsum wall cladding and partitions in the master bedroom. N/A | LOT | 1 | 2,112 | QAR 2,112 | 100% | |
1.1.6 | Master bathroom: new niche opening and plastering, 500mm x 800mm, incl. lintel 200mm x 1200mm. N/A | LOT | 1 | 228 | QAR 228 | 100% | |
1.1.7 | Master bathroom: new niche opening and plastering, 300mm x 1300mm, incl. lintel 200mm x 1500mm. N/A | LOT | 1 | 228 | QAR 228 | 100% | |
1.1.8 | Bedroom 1 bathroom: new niche opening and plastering, 200mm x 1000mm, incl. lintel 200mm x 1200mm. N/A | LOT | 1 | 228 | QAR 228 | 100% | |
1.1.9 | Bedroom 2 bathroom: new niche opening and plastering, 200mm x 1000mm, incl. lintel 200mm x 1200mm. N/A | LOT | 1 | 228 | QAR 228 | 100% | |
1.1.10 | Bedroom 3 bathroom: new niche opening and plastering, 200mm x 500mm, incl. lintel 200mm x 700mm. N/A | LOT | 1 | 228 | QAR 228 | 100% | |
VO-04 Parquet Substrate Tiles QAR 810 100% | |||||||
1.1.11 | Supply of low-cost ceramic/porcelain base tiles to receive parquet flooring. N/A | SQM | 54m² | 15 | QAR 810 | 100% | |
VO-05.1B Doors QAR 97,288 0% | |||||||
1.1.1 | Supply and install single swing door, MDF + red oak, W1000 x H2300mm. N/A | item | 14 | 4,553 | QAR 63,739 | 0% | |
1.1.2 | Supply and install double swing door, MDF + red oak, W1500 x H3800mm. N/A | item | 1 | 12,846 | QAR 12,846 | 0% | |
1.1.3 | Supply and install double sliding door, MDF + red oak, W2000 x H2300mm. N/A | item | 1 | 9,128 | QAR 9,128 | 0% | |
1.1.4 | Supply and install double sliding door, MDF + red oak, W3000 x H2300mm. N/A | item | 1 | 11,574 | QAR 11,574 | 0% | |
VO-05.2C Wall Stone QAR 165,900 0% | |||||||
1.1.5 | Supply and install Omani stone cladding with mechanical fixation (50% of Majlis). N/A | SQM | 395m² | 420 | QAR 165,900 | 0% | |
VO-05.3C Stone Steel Structure QAR 14,400 0% | |||||||
1.1.7 | Supply and install complete steel structure framework for villa front facade. N/A | SQM | 1m² | 14,400 | QAR 14,400 | 0% | |
VO-05.4C Shower Glass QAR 15,405 0% | |||||||
1.1.8 | Supply and install 12mm tempered clear glass shower partitions (all bathrooms). N/A | LOT | 1 | 15,405 | QAR 15,405 | 0% | |
VO-05.5C Sliding Gate QAR 11,400 0% | |||||||
1.1.9 | Supply, fabrication and install manually operated sliding gate (mild steel), 3000mm x 5000mm. N/A | LOT | 1 | 11,400 | QAR 11,400 | 0% | |
VO-05.6C Qalex Upgrade QAR 12,255 91% | |||||||
1.1.12 | Additional charge for upgrading U-shaped windows from UPVC to Qalex aluminum system. N/A | item | 1 | 12,255 | QAR 12,255 | 91% | |
VO-05.7C Exterior Tiles Walkway QAR 16,576 60% | |||||||
1.1.12 | Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (walkway & driveway). N/A | SQM | 185m² | 90 | QAR 16,576 | 60% | |
VO-05.9C Exterior Tiles PH Balcony QAR 5,824 60% | |||||||
1.1.12 | Supply of exterior high-strength 20mm x 800mm x 400mm ceramic stone composite floor tiling (PH balcony). N/A | SQM | 65m² | 90 | QAR 5,824 | 60% | |
VO-05.9.8 Car Shade QAR 19,902 0% | |||||||
1.1.12 | Supply and install custom car shade 6000mm x 5000mm, galvanized steel frame, PVC ceiling. N/A | UMIT | 1 | 19,902 | QAR 19,902 | 0% | |
VO-05.9.9 Bathroom Wood Panels QAR 8,970 0% | |||||||
1.1.12 | Supply and install premium flat veneer-faced MR MDF wall panels to bathroom walls above toilets. N/A | SQM | 25m² | 359 | QAR 8,970 | 0% | |
VO-06.01 Parquet QAR 29,520 0% | |||||||
1.1.12 | Supply and install premium European waterproof engineered parquet flooring, 20mm x 120mm planks with acoustic underlay. N/A | SQM | 205m² | 144 | QAR 29,520 | 0% | |
VO-06.02 PVC Skirting QAR 6,162 0% | |||||||
1.1.12 | Supply and install premium white PVC skirting, 150mm high, all villa hallways and bedrooms. N/A | LM | 395 | 16 | QAR 6,162 | 0% | |
VO-06.03 Water Holding Tank QAR 14,280 60% | |||||||
1.1.12 | Underground drinking water holding tank 2500mm x 2500mm x 2000mm — reinforced concrete, complete. N/A | LS | 1 | 14,280 | QAR 14,280 | 60% | |